The project begins with the design of the fiber build. Once the design is set, field engineers determine if modifications to any poles are required in order to support the fiber and the steel strand that accompanies it. Poles may need to be moved to make more space, or they may need to be replaced with stronger or taller poles.
During the first phase, inspectors will also “ride out” the build, visiting every location throughout the project area and making notations of changes that may need to be made. During make-ready engineering and assessment, we also make sure every member in the territory is included in the build. This phase can take 2 to 4 weeks.